Clarification of the claim for recognition of acts of completed works as valid, for debt collection and penalties
Specialized Interdistrict Economic Court of Almaty
273b Baizakov St., Turksib district, Almaty.
from the Plaintiff: LLP "C..kz»
represented by Director D. O.F.
BIN …
Almaty, Tole bi str., ..., 13th floor.
8 (727) …….
Representative by proxy:
Law and Law Law Firm
BIN 201240021767
79 Abylai Khan Ave., office 304, Almaty.
info@zakonpravo.kz / www.zakonpravo.kz
+7 708 971 78 58; + 7 727 971 78 58.
Clarification of the claim
There is a civil case in your proceedings No. 7527-24-00-2/10607 dated 08/07/2024 on the claim of "C" LLP. kz" (Hereinafter referred to as the Plaintiff) to Kaz...-1 LLP (Hereinafter referred to as the Defendant) on the recognition of acts of completed works as valid, on debt collection and penalties.
In this case, we have not provided explanations in the claims regarding the calculation of the amount of the claim. The price of the claim in this case is 3,144,933 tenge. Of these, 1,075,364 tenge is the amount of the penalty, and the remaining 2,069,569 tenge is the amount owed under Contract No. 77 dated October 19, 2020, Additional Agreement to the Subcontract No. 77 dated October 18, 2021 and under Subcontract No. 01.2/PD/2021 dated February 12, 2021.
The debt is calculated as follows:
· 802,853 tenge according to the reconciliation act of mutual settlements signed by the parties for the period 01.01.2021 to 03.12.2021 under subcontract No. 77;
· 120,000 tenge according to the act of completed works No. 3 dated 31.01.2022 under subcontract No. 77;
· 728,000 tenge according to the act of completed works No. 4 dated 31.01.2022 under subcontract No. 77;
· 269,611 TENGE unpaid amount according to the act of completed works No. 45 dated 09.11.2021 under subcontract No. 01.2/PD/2021;
· 62,300 tenge according to the act of completed works No. 2 dated 31.01.2022 under the supplementary agreement to the Subcontract No. 77;
· 86,805 tenge unpaid amount under the act of completed works No. 52 dated December 27, 2021 under the supplementary agreement to the Subcontract No. 77.
About the penalty fee. The penalty for late payments for works and services rendered, which amounted to 1,075,364 tenge, was calculated in the form of a table in the claim and the attached table to the claim.
We ask the Court to take note of this clarification on the claims.
With respect,
Representative by proxy: Kenesbek I.M.
Attention!
Law and Law Law Law draws your attention to the fact that this document is basic and does not always meet the requirements of a particular situation. Our lawyers are ready to assist you in legal advice, drawing up any legal document suitable for your situation.
For more information, please contact a Lawyer / Attorney by phone: +7 (708) 971-78-58; +7 (700) 978 5755, +7 (700) 978 5085.